(1) The utilisation of hazardous and other wastes as a resource or after pre-processing either for co-processing or for any other use, including within the premises of the generator (if it is not part of process), shall be carried out only after obtaining authorisation from the State Pollution Control Board in respect of waste on the basis of standard operating procedures or guidelines provided by the Central Pollution Control Board.

(2) Where standard operating procedures or guidelines are not available for specific utilisation, the approval has to be sought from Central Pollution Control Board which shall be granting approval on the basis of trial runs and thereafter, standard operating procedures or guidelines shall be prepared by Central Pollution Control Board:

Provided, if trial run has been conducted for particular waste with respect to particular utilisation and compliance to the environmental standards has been demonstrated, authorisation may be granted by the State Pollution Control Board with respect to the same waste and utilisation, without need of separate trial run by Central Pollution Control Board and such cases of successful trial run, Central Pollution Control Board shall intimate all the State Pollution Control Board regarding the same.

(3) No trial runs shall be required for co-processing of waste in cement plants for which guidelines by the Central Pollution Control Board are already available; however, the actual users shall ensure compliance to the standards notified under the Environment (Protection) Act,1986 (29 of 1986), for cement plant with respect to co-processing of waste:

Provided that till the time the standards are notified, the procedure as applicable to other kind of utilisation of hazardous and other waste, as enumerated above shall be followed.

10. Standard Operating Procedure or guidelines for actual users.- The Ministry of Environment, Forest and Climate Change or the Central Pollution Control Board may issue guidelines or standard operating procedures for environmentally sound management of hazardous and other wastes from time to time.