Specifications for Package Water Treatment Plant

Ref: Schedule of Rates, MJP, Pune Region, 2012-2013

Designing   (aesthetically),   providing,fabricating  Package  Water  Treatment Plant at the shop, transporting to site,
installing, testing and commissioning at the site, giving necessary one month's free test and trail run with guarantee for
one year, etc. complete Prefabricated Package Water  Treatment Plant comprising following :

1) Rapid  mixing  channel  in  M.S.  sheets and M.S. baffle.

2)   Flocculator  not  less  than 10  minutes detention,  in  M.S.  prefabricated  box,flocculation  being  achieved  either  by glass  pebbles  of  graded  size  or  PVC tetrapod  or  equivalent  arrangement  to ensure good floc formation.

3) Plate or tube settlers of not less than 30 minutes detention in M.S. prefabricated box, the plates / tubes mounted in the
settler basin with inclination of not less than 60 degree to horizontal.

4)  Rapid   sand   gravity   filter   in   M.S. prefabricated  box  with  filter  sand  not less than  500 mm thick, supported on false  floor  below  with  polypropylene nozzles spaced at not more than  500 mm centres in either direction.

5)  Backwashing,  inlet  facilities  only  shall be provided. Department shall provide either ESR giving  8 to  10 M head at
filter nozzles or backwash pump, having flow  rate  of  0.6  Cum  per  minute  per square metre of filter bed.  (Limit upto
5.0 M. from W.T.P. face)

6) All civil works for foundation, consisting of raised RCC platform above G.L. or walls in B.B. masonry or UCR masonry
shall be provided as per needs at site.

7)    Bypass  in  the  form  of  pipes  or  M.S.channels   included   in   the   design,effecting bypass of such new tank and
filter individually or both. (Limit upto 5.0 M. from W.T.P. face)

8)  The entire M.S. fabricated tank provided with FRP lining  (5 mm thick) to inside face   in   contact   with   water   epoxy painting-  two  coats  with  one  coat  of primer  on  outside.  The  thickness  of plates employed shall not be less than 6 mm

9)  Alum dosing and mixing arrangements to be provided in twin tanks, each of 8 hours  capacity,  capable  of  importing
does of 20 ppm with 5% solution. The alum  tanks  provided  with  a  dose  in steps of 5 ppm and entire unit mounted
on the top of flocculator / settler box, in the form of prefabricated structure, with access platform and ladder. Alum boxes
with FRP lining (5 mm thick) inside and epoxy paint two coats with one coat of primer on outside.

10)   Both  flocculator  and  settling  basins provided with hopper bottom with slope not   less   than 45   degrees   to   the horizontal   drain   pipes   and   valves provided to both flocculator and settling basin.

11) Flow   ratings   to   conform   following parameters :
a) Velocities in channels not to exceed 0.6 M./Second.
b) Velocities  in  filter  outlet  pipes  and valves not to exceed 1 M./Second.
c)  Velocities  in  interconnecting  pipe  and controls not to exceed 1M./Second.
d)   Backwash with air : Not required.
e)  Backwash with water : Not less than 0.6  M./ Sqm. of filter bed area in filter box.

12) Free  board  for  all  units  not  less  than 300 mm