Specifications for Units in Moving Media Bioreactor
1. Inlet Chamber
Designing, providing and constructing 1 No. RCC (M-25) inlet chamber designed for the peak flow including necessary excavation in all types of strata including walkway all around the periphery. Each compartment will have CI gates with extension rod, head stock,operating wheels, GI pipe railing, etc.
The work includes providing and making necessary arrangements to connect the flow to screen chamber by approach channel as directed and as per specifications.
2. Screen Chamber
Designing, providing, constructing, 2 Nos testing and commissioning of screen chamber, designed for peak flow in RCC (M-25), including walkway 1.2 m wide with GI pipe.
3. Grit Separator
Designing, providing and constructing 2 Nos detritor type grit removal mechanism in RCC (M-25) capable of removing 100% 0.2 mm size particle and above, having specific gravity 2.30 designed for peak flow with suitable arrangement of separation of grit from putrescible solids including providing and making necessary arrangements of Jb-1. Inlet and outlet channels of required sizes as make be required to connect the flow to connecting unit, etc. complete including hydraulic testing for watertightness of structure having minimum FB of 0.3 m, washout arrangement to grit chamber and platform 1.2 m wide RCC walkway with GI pipe handling shall be provided.
A pit for collecting grit conveyed by conveyor shall be provided. It should be suitable to handle the grit for carting. All arrangements shall be as detailed specifications and as directed.
4. MMBR / FAB Tank
Designing, providing and constructing in 1 No.RCC (M-25) biological reactor tank for removal of BOD along with nutrient removal to handle the average flow and having hydraulics suitable to handle peak flow conditions with suitable 1.2 m wide walkway, expansion joints as required, including foundation, etc as per specifications. The tank shall be equipped with inlet and outlet arrangement, air blowers for supply of air, coarse bubble diffusers and aeration grid in SS 304, PP carrier bio media, etc. FB of 0.5 m and SWD as required should be complete as per detailed specifications.
5. Secondary Clari Settler
Designing, providing and constructing in 1 No.RCC (M-25) watertight secondary clarisettler having SWD of 3.75 m + 0.5 m
FB and has tube media in the clarification zone to provide additional surface area for settling. The settler shall be provided with a scraper mechanism in MS with epoxy painting for collecting the settled solids at the bottom (bottom slope 1:12). The central feed well shall be made of MS with epoxy painting from both faces and well tiffened. The sewage will be admitted in the feed well and then will move outwards towards periphery slowly and continuously over a weir and will be collected in a launder.
6. Chlorine Contact Tank
Designing, providing and constructing 1 No chlorine contact tank of adequate capacity to deal with average flow. The contact time provided is 30 mm to achieve 99.99% reduction in coliform during average flow condition. Chlorine dosage will be as per standard provisions including designing, providing and constructing water supply provision for chlorination, including providing dewatering and bypass arrangement for joining to final effluent mains and outlet weir, etc. complete. The effluent quality should match with the standards laid down by Maharashtra Pollution Control Board and as per obligatory provision and as detailed specification and as directed by Engineer-in-charge.
7. Chlorinator and Chlorinator Room / Tonner Room
Designing, providing and constructing 1 No. vacuum type chlorinators having adequate capacity for dosage of adequate chlorine to ensure 99.99% coliform reduction as per obligatory provisions, detailed specifications with necessary provision having chlorinator room of adequate size. The chlorinator equipment shall include chlorine cylinders / tonners, piping,valves, measuring, controlling equipments, safety devices, lifting equipment, etc. complete as per IS 10553 (Part II) 1982. The tonner room should have min. 3 MT capacity crane for loading and unloading facility Tonner storage should be distinctly isolated and should have min. storage space as per the detailed specifications and as per gas law 1981 and factory act shall be provided. All other matching amenities shall be provided, 5 MT gantry rail shall be provided for full length of tonner room at 6 m ht. from level of tonner room with outlet.
8. Sludge Sump
Designing, providing and constructing of 1 No. sludge sump and pump for discharging sludge to sludge thickener using MS pipe, etc. complete as per detailed specification.
9. SIudge Thickener
Designing, providing and constructing watertight of sludge thickener - gravity type in RCC (M-25) with inlet and outlet pipes, central feed well, sludge it and sludge removal arrangement, grouting wherever necessary with walkway all around of 1.20 m with GI pipe railing interconnecting CI pipes all complete as per specifications, having bottom slope 1:8 and 3 m SWD with necessary fixed bridge scraper arrangement as per detailed specifications and necessary inlet and outlet arrangement, all other arrangement as per detailed specifications. 1 No.
10. Sludge Centrifuge Platform with Centrifuge
Designing, providing, constructing and installing including foundation, etc sludge centrifuge to handle the sludge flow of 1 day in 18 hrs per unit with sludge dewatering unit, drain, etc. complete is per specification. Sludge centrifuge with necessary arrangements as per detailed specification mentioned in tender and obligatory provisions to be provided with satisfactory functioning. 1 No.
11. Outfall Sewer
Designing providing constructing appropriate outfall sewer of RCC NP2 pipe to discharge treated effluent, untreated effluent from outlet chamber (after basin / chlorination tank) to the local Nallah at the point shown on the drawing including necessary chambers for inspection and cleaning including excavation dewatering refilling concrete, encasing / bedding concrete. 1 No.
12. Piping Work in CI LA class including Sluice Valves, Reflux Valves, MS Gates Providing, laying and jointing pipes Lot other than those already included in the above items for interconnection, bypass drains, etc. of all units including adequate number of manhole chambers. The item includes excavations, refilling and hydraulic testing of pipes, valves, gates, accessories and cost of jointing materials. The item includes required channels with gates or interconnection of units, bypass drains, etc. for ill units as directed, etc complete as per detailed specifications.
13. Administrative Building cum Laboratory (G+1)
Designing, providing and constructing administrative building, office cum laboratory including stores. This shall be building having appropriate carpet area, at ground floor and at first floor complete as per specifications including necessary excavation, foundation in RCC M-20 framed structure, BB masonry (IInd class in CM 1:6), 20 mm cement plaster in CM 1:3, inside and outside painting, aluminum door and window with glass panels, mosaic tile flooring and skirting and all other allied items, fixtures, fastening, electrification arrangement, water supply arrangement, etc complete.
The building will have laboratory on upper floor of administrative building and should have complete control of every unit as per laboratory equipment, beautification, telephone and intercom arrangement and wireless system.