Specifications for Units in Cyclic Actvated Sludge Process

1. Inlet Chamber
Designing,  providing,  and  constructing RCC (M-250) inlet chamber for the peak low  of 2  DWF  including  necessary
excavation   in   all   types   of   strata including   walkway   all   around   the periphery.
Each compartment will have phosphor bronze steel gates with extension rod, head stock, operating wheels, GI pipe
railing, etc. The work includes providing and making necessary arrangements to connect the flow to screen chamber by
approach  channel  as  directed  and  as per specifications.

2. Screen Chamber
Designing,    providing,    constructing, testing  and  commissioning  of  screen chamber, designed for average 1 DWF
and maximum peak flow of  2 DWF in RCC  (M-250),  including  inlet  pipe  / channel from inlet chamber, outlet pipe
channel to detritus tank, free board of 0.5  m minimum, RCC walkway  1.2 m wide with GI pipe railing, RCC staircase
of  1.2  m  width  from  GL  to  screen chamber.

3. Detritus Tank
Designing,  providing  and  constructing continuous  grit  removal  type  Detritus Tank,  mechanically  operated  in  RCC
(M-250) capable of removing  100% of 0.2 mm size particle and above, having specific gravity  2.30, designed for one
peak 2 DWF with suitable arrangement of  separation  of  grit  from  putrescible solids.  Inlet  and  outlet  channels  of
required  sizes  as  may  be  required  to connect the flow to connecting unit etc. complete including hydraulic testing for
watertightness   of   structure   having minimum   FB   of 0.3   m,   washout arrangement   to   grit   chamber   and
platform 1.2 m wide RCC walkway with GI pipe handling shall be provided. A pit for collecting grit conveyed by conveyor
shall be provided. It should be suitable to   handle   the   grit   for   carting.   All arrangements   shall   be   as detailed specifications and as directed.

4. CASP Basins
Designing, providing and constructing in RCC(M-250) CASP   basins   for biological  removal  of  BOD  along  with nitrification, denitrification, Bio-P removal  in  compartments  to  handle combine flow of  1 DWF incoming flow and    recirculation flow including construction  of  selector  compartments and   providing 1.2   m   wide   clear approach  walkways,  expansion  joints wherever  necessary, including foundations,  etc  as  per  specifications.
Peak factor shall be  2, F/M ratio shall be 0.15, complete with air blowers, fine diffused aeration grid  / equipment and FB  0.5  m  and  SWD  as  required.  DO level  in  basin  to  be  minimum 2  mg/l complete  with‘Oxygen  Uptake  Rate control    system    and    all    related instruments,  stainless  steel  decanters and automation works MLSS concentrations shall be 2000-5500 mg/l or more. MLVSS to MLSS ratio to be 0.8. HRT shall be between 12 to 13 hrs and  SRT  suitable  for fully  digested sludge. It should have all other related works as per detailed specification. In case CASP is designed to    achieve N,P removal  HRT  shall  be  between  15-18 hrs and SRT shall be suitably provided to a


5. Chlorine Contact Tank
Designing,  providing  and  constructing chlorine  contact  chamber  of  adequate capacity to deal with  1 DWF average
flow. The chlorine contact tank should be 30 min capacity, during average flow to  achieve  99.99%  coliform  reduction.
Chlorine  dose  shall  be  maintained  as per   standard   provisions,   including designing,  providing  and  constructing
water  supply  provision  for  chlorination including   providing   dewatering   and bypass  arrangement,  jointing  to  final effluent  mains  and  outlet  weir,  etc  complete.  The  effluent  quality  should match with the standards laid down  by Maharashtra  Water  Pollution  Control Board and as per obligatory provision and  as  detailed  specification  and  as
directed by Engineer-in-charge.

6.  Chlorinator and Chlorinator Room  / Tonner Room
Designing,  providing  and  constructing chlorinators  vacuum  type  2  Nos.  with auto   switchover   facility   and  having capacity   for   dosage   of   adequate chlorine  to  ensure 99.99%  coliform reduction  as  per  obligatory provisions and    detailed    specifications    with necessary provision  of         having chlorinator room of adequate size. The chlorinator equipment shall include cost of  chlorine  cylinders  /  tonner  piping, valves,   measuring   and controlling equipments,   safety   devices,   lifting equipments,  etc.  complete  as  per  IS- 10553 (Part II) 1982. The tonner room should  have  minimum  3  MT  capacity hoist for loading and unloading facility Tonner  storage  should  be  distinctly isolated  and  should  be  for  minimum storage space as directed in the design specification and as per Gas Laws 1981 and Factory Act shall be provided. All other   matching   amenities   shall   be provided. 5  MT  gantry  rail  shall  be provided for full length of tonner room at 6 m height from level of tonner room, with outlet chamber and treated effluent outlet  channel,  etc.  complete  as  per detailed specification.


7. Sludge Sump
Designing, providing and constructing of sludge   sump   and   pump  house  of appropriate  size  with  pumps,  ceiling
height  minimum  6  m  over  sump  for discharging sludge to centrifuge using CI pipe, etc. complete as per detailed
specification.


8.   Sludge   Centrifuge   Platform   with Centrifuges
Designing,  providing,  constructing  and installing   including   foundation   etc sludge centrifuge to handle the sludge
flow of 1 day in 20 hours per unit with sludge   dewatering   unit,   drain   etc. complete  as  per  specification.  Sludge
centrifuges with the        necessary arrangement as  per        detailed   specification  mentioned  in  tender  and
obligatory provisions to be provided with satisfactory functioning.

9. OutfaIl Sewer
Designing,  providing  and  constructing appropriate outfall sewer of RCC NP2 pipe, to discharge treated effluent from
outlet chamber after chlorination tank to the local nallah at the point shown on the    drawing    including    necessary
chamber  for  inspection  and  cleaning including necessary excavation, dewatering, refilling, concrete encasing
/ bedding concrete steps to reach the nallah  bed  level,  pitching  and  energy dissipation  chamber  in  nallah  portion,
etc.  complete  upto  50  m  length  RCC NP2 pipe line and including all above items.


10. Piping Work in CI-LA class including Sluice Valves, Reflux Valves, MS Gates
Providing,  laying  and  jointing  pipes other than those already included in the above items for interconnection, bypass
drains,   etc.   of   all   units   including adequate  number     of     manhole chambers.The  item includes excavations,   refilling   and   hydraulic testing    of    pipes,    valves,    gates  accessories   and   cost   of   jointing
materials. The items includes required channels with gates for interconnection of units, bypass drains, etc. for all units
as   directed,   etc   complete   as   per detailed specifications.


11. Administrative    Building   cum Laboratory (G+1)
Designing,  providing  and  constructing administrative   building,   office   cum laboratory  including  stores.  This  shall be a building having appropriate carpet area  at  ground  floor  and  at  first  floor complete as per specifications including necessary  excavation,  foundation  in RCC   M-200   framed   structure   BB masonry (IInd class in C.M. 1:6), 20 mm cement  plaster  in  CM  1:3  inside  and outside  painting.  Aluminium  door  and window  with  glass  panels,  mosaic tile flooring and skirting and all other allied items, fixtures, fastening, electrification arrangement, water  supply
arrangement, etc. complete  


The  building  will  have  laboratory  on upper  floor  of  administrative  building and  should  be  so  centralized  that  it should not be attached with any unit but should have complete control of every unit   as   per   laboratory   equipment,
beautification,  telephone  and  intercom arrangement and wireless system.